Üçpınar WPP2019
Siemens Gamesa’s first turnkey WPP in Turkey was construction by Tanınmış İnşaat.
Within the project, 33 SWT 3.4 MW turbine foundations, platforms, 20 km of roads and 20 km of cable trench were constructed.
- Number of Turbines: 33
- Total Capacity: 110 MW
- Turbine Supplier: Siemens Gamesa
- Scope: Foundation Design, Turbine Foundation, Road/Platform Earthworks, Cable Trench
Date 2019
Company Siemens Gamesa
Location Çanakkale – Lapseki